North Coventry recently issued the following announcement.
ATTENTION :LAURELWOOD ROAD AREA RESIDENTS
North Coventry Municipal Authority Water and Sewer Service Improvements Public Notice
The North Coventry Municipal Authority has contracted with Joao Bradley Construction Company to conduct utility improvements including the construction of replacement water mains and sewer mains on several Township roads this Spring 2022.
The contractor is anticipated to begin water main construction on March 24, 2022, weather dependent, on Root Avenue, then proceeding to River Road, and Schuylkill Road (Rt. 724).
Construction on sewer mains is anticipated to begin mid – late April 2022 on Laurelwood Road, from Greenbriar Lane to River Road.
Residents should expect intermittent closures of roadways between the hours of 9:00 a.m. – 3:00 p.m., and construction equipment staging in the vicinity of the project area. The contractor will coordinate with residents to allow access to homes during construction, but on road parking during construction will be very limited.
The construction work is projected to be completed by the end of May 2022. The Authority appreciates the patience of the public during the construction period in order to make necessary infrastructure improvements.
If you have questions related to the project, please contact the North Coventry Municipal Authority at 610-326-1064 or visit their office located at 1485 E. Schuylkill Road, Pottstown, PA 19465.